Dodd Civil provided Civil Engineering services for the design and build of a new $55M state-of-the-art manufacturing and distribution warehouse for Sistema Plastics in Mangere, Auckland.
Sitting next to Auckland International Airport, the site covered an area of 100,000m2 with the new building footprint covering an area of 50,000m2. The project involved 5,3000m3 of cut-to-fill earthworks, 12,500m2 of new carparking pavement, 17,200m2 of new heavy-duty pavement, 5,200m2 of truck access pavement and 150m of timber retaining.
Slide title
Aerial of Sistema Facility
Button
Slide title
Aerial of Sistema Facility
Button
Slide title
Sistema Building Entrance
Button
Slide title
Sistema Facility - Heavy Duty Pavement
Button
THE PROJECT
Pavement design
Stormwater / Wastewater design
Engineering designs and associated documents
Construction observation
Retaining
Subsoil drainage
CHALLENGES & SOLUTIONS
The short timeframe and a fixed deadline required careful resourcing to stay on program.
We worked successfully with a multidisciplinary team, including main Contractors, subcontractors, architect, planners and structural engineers to bring the project in ahead of schedule.
There were many design changes made during construction to meet the changing client needs of this complex project.
AWARD WINNING PROJECT
SISTEMA PLASTICS MANUFACTURING FACILITY
Rider Levett Bucknell Property Industry Awards 2017
Yardi Industrial Property Award - Best in Category